Ending a sprint - Do you know what to do with partially completed PBI?
  v5.0 Posted at 24/05/2018 3:16 PM by Ulysses Maclaren
At the end of a sprint, if a PBI has not been completed and therefore cannot be marked as done: 
  1. ​​​Update the Effort to be just what is remaining
  2. If there has been scope creep, but the original Acceptance Criteria has been met, it might be a good opportunity to mark it as done and move any scope creep tasks into a V2 of the PBI, which can then be prioritised in the backlog by the Product Owner