Rule #24
Reports - Do you schedule the Burndown and Stories Overview reports to be emailed to the team every day?
  v7.0 Posted at 19/10/2011 4:43 PM by cindywang
Each time you start a new sprint (aka iteration) you should have the 2 key reports (Burndown and Stories Overview) automatically sent to the team’s inbox each night. Every scrum meeting you should check the burn down report or the physical story board.

The team will get these two reports in their inboxes each evening.


Figure: "Burndown and Burn Rate" report example


Figure: Sample report for "Stories Overview"

For more information, If you don't know how to schedule the emails check out the following:
 
Figure: Find the reports by right clicking Reports | Show Report Site… 


Figure: Select “Project Management” on the report website


Figure: Then go to “Burndown and Burn Rate” 


Figure: Subscription step 1 - Edit


Figure: Subscription step 2 - Manage subscribers and update sprint


Figure: Subscription step 3 - Update schedule


Figure: Subscription step 4 - Edit parameter values for Burndown

Now, you have to set up the reports for Stories Overview. Go back to the report website and select "Stories Overview" this time. 


Figure: Click "Stories Overview" 

Repeat the steps 1 to 3 you've just done for the "Burndown and Burn Rate" report


Figure: Subscription step 4 - Edit parameter values for Stories Overview

 

 

 