Do you know the numbers you give clients?
v3.0
Posted at
20/10/2010 7:56 PM by
system
Rule Intro
When working on an hourly basis, you can confuse clients when sometimes you try to talk about a few hours here and a few hours here or there.
Page Content
Simply things and just give them these 3 numbers:
| $ Billed to date |
__$xx__(accurate on Tuesday) |
| Burndown Days Remaining |
__8__ |
| Calendar Days Booked |
__4days x 2__ |
| Next meeting (for Review and Retro) |
|
Hi Andrew,
Please find the Burndown report below. I have looked at a few tasks with Zune and re-estimated them.
- Product owner:Andrew
- Scrum master:Paul
- Team:Mark L,Zune,Tristan,Trevor
- $ Billed to date:$20,000
- Days remaining:(around 50 hours based on chart below)=7+days
- Days booked in are 4 days x 2
- ML and ZV - Mon 5th
- ML and ZV - Tue 6th
- ML and ZV - Mon 12th
- ML and ZV - Tue 13th
- Only the 14th we will
- Move any remaining tasks to Sprint 4
- Have a Review Meeting (show and tell) at 10am – 2 hours
- Have a Retrospective Meeting at 12 noon – 2 hours
- Have a Planning Meeting at 2pm
Please let us know if you have any questions or concerns.